Slide

12 MMSCFD nitrogen rejection unit using NiTech® technology for coal mine methane application.  (Replacement due to severe tornado damage to the original facility) Project included the completion of structural skid fabrication, supply and installation of the required NiTech® NRU interconnecting piping, valves and fittings, supply and installation of the inlet gas dehydration system, and supply and installation of the required instrumentation including a computer-based PLC control system. BCCK’s full EPC scope included field installation.